N.J. Admin. Code § 7:14-2.15

Current through Register Vol. 56, No. 11, June 3, 2024
Section 7:14-2.15 - Substantial and final completion of pipe projects; contractor's guarantees
(a) The contractor shall notify the owner/engineer in writing when the contract work is substantially complete as defined by 7:14-2.8(d). Within a reasonable time, the owner/engineer shall inspect the work.
(b) If the owner/engineer considers the work to be substantially complete, and before the Certificate of Substantial Completion is issued, the contractor shall:
1. Submit a construction schedule for the remaining work to be completed, and
2. Warrant and guarantee, for a period of one year or for a period as otherwise specified, from the date of Substantial Completion, that the completed work is free from defects due to faulty materials, equipment or workmanship. The Performance Bond shall remain in effect through the guarantee period.
(c) If the owner/engineer does not consider the work to be substantially complete, the engineer shall notify the contractor in writing, listing the items to be completed or corrected.
1. The contractor shall correct or complete items identified in writing within a reasonable time as specified in the contract documents, including repairs of any damage resulting from such defects to other work completed under the contract.
2. If the contractor fails to make such corrections within a reasonable time as specified in the contract documents, the owner may do so and charge the costs incurred, including direct and indirect costs, to the contractor.
(e) Before the Contractor has received notification of substantial completion, the owner/engineer may submit a request to the contractor to use a functional portion of the work if:
1. Such use does not significantly interfere with construction on any portion of remaining work to be completed, and
2. The conditions of such use shall be identified in the Certificate of Substantial Completion when issued by the owner/engineer.
(f) Final completion shall be that point at which the contract is completed, defective work corrected and clean up work accomplished. Unless a Certificate of Substantial Completion has been issued, the guarantee period shall begin upon certification of final completion by the engineer.

N.J. Admin. Code § 7:14-2.15

R.1984 d.339, effective 8/6/1984.
See: 16 New Jersey Register 1147(a), 16 New Jersey Register 2102(b).