N.J. Admin. Code § 6A:26-3.10

Current through Register Vol. 56, No. 12, June 17, 2024
Section 6A:26-3.10 - Design and construction of ROD school facilities projects
(a) The provisions of the Public School Contracts Law, 18A:18A-1 et seq., and implementing rules are applicable to any school facilities project constructed by a school district.
(b) Prior to UCC approval for construction of a school facilities project, a school district shall submit to the Division the final plans and specifications for final approval pursuant to 6A:26-5.4.
(c) Upon completion of a school facilities project by a school district, the school district shall submit to the Commissioner a plan for school facility maintenance in accordance with N.J.A.C. 6A:26-20. All plans shall include a provision for a maintenance reserve fund. All maintenance reserve funds created in accordance with N.J.A.C. 6A:26-20 shall be funded annually with two-tenths of one- percent of the net replacement cost of the school facility, which shall be included in the annual budget of the school district. The monies in the maintenance reserve fund may be withdrawn at any time during the year to fund the maintenance mandated by N.J.A.C. 6A:26-20. The net replacement cost of the school facility shall equal the area cost allowance multiplied by the gross square footage of the building.

N.J. Admin. Code § 6A:26-3.10

Amended by R.2001 d.367, effective 10/1/2001.
See: 33 N.J.R. 1809(a), 33 N.J.R. 3482(a).
In (b), inserted "UCC approval for" and updated N.J.A.C. reference; deleted (c); recodified (d) as (c); and in new (c), deleted "school" preceding "district" in the third sentence.
Amended by R.2007 d.81, effective 3/19/2007.
See: 38 N.J.R. 4533(a), 39 N.J.R. 899(a).
Inserted "school" preceding "district" throughout; and in (c), substituted "N.J.A.C. 6A:26A" for "the Commissioner's regulations to be adopted pursuant to N.J.S.A. 18A:7G-9(b)(3)" three times.
Amended by R.2013 d.145, effective 12/16/2013.
See: 45 N.J.R. 1026(a), 45 N.J.R. 2557(a).
Section was "Design and construction of non-Authority school facilities projects". In (b), inserted "to the Division" following submit, and deleted "to the Division" following "specifications"; and rewrote (c).