Section 19:39-4.1 - Subcontractor replacement on school facilities projects
(a) A construction or goods and services contractor shall not replace an SBE or DVOB subcontractor, except where such contractor is in breach of its subcontract and the SDA has provided the contractor its prior written consent to the replacement.
(b) A request for replacement shall be in writing, with complete justification for the request. The contractor must have the written approval of the SDA before such a replacement can be made, regardless of the reason for the replacement.
(c) The contractor shall make a good faith effort to find another SBE or DVOB firm, as applicable, to perform at least the same amount of work as had been allocated to the original SBE or DVOB subcontractor.

N.J. Admin. Code § 19:39-4.1

Amended by 47 N.J.R. 1651(c), effective 7/6/2015
Amended by 54 N.J.R. 2401(a), effective 12/19/2022