N.J. Admin. Code § 19:38B-7.1

Current through Register Vol. 56, No. 11, June 3, 2024
Section 19:38B-7.1 - Contract approval and execution
(a) Upon approval of a recommendation for award by the Board, the Authority shall issue a Notice of Award letter to the bidder. The Notice of Award is not binding on the Authority until the Authority has executed the contract, and the Notice of Award does not authorize the commencement of work under the contract. No person shall perform any work in furtherance of the contract unless and until the Authority executes the contract and issues a Notice to Proceed.
(b) The Notice of Award letter shall contain a list of the additional documents required to be submitted by the bidder with the executed contract, including the requirements for payment and performance bonds. The Notice of Award will specify the time within which the bidder must submit to the Authority the executed contract and other documents required by the Notice of Award. Within the time period specified in the Notice of Award, the bidder shall properly and duly execute the contract and deliver to the Authority the executed contract, as well as performance and payment bonds and all other documents required by the RFP or the Notice of Award letter.
(c) Each payment and each performance bond must be in an amount at least equal to the total contract price.
1. All bonds shall comply with the requirements of this chapter and relevant State statutes. All bonds submitted by the bidder shall be issued only to the bidder, and shall conform to the provisions of 2A:44-143 through 147 and shall indicate aggregate bonding limits.
2. Bonds shall be issued only by companies authorized to transact business in the State of New Jersey.
(d) If the bidder fails to return the required documents within the time specified by the Authority, the Authority may take whatever action is appropriate and authorized by law including, but not limited to, withdrawing or cancelling the notice of award to the delinquent bidder and awarding the contract to the next-highest ranked bidder, cancelling the procurement or proceeding to recover under the bid bond submitted.
(e) Upon the successful contractor's submission of any required documentation or materials as specified in the notice of award, and the Authority's acceptance of such documents, the Authority will execute the agreement and provide the successful contractor with a fully-executed agreement.