EMR is less than or equal to .80 | +30 percent |
EMR is greater than .80 but less than or equal to .90 | +20 percent |
EMR is greater than .90 but less than or equal to 1.00 | +10 percent |
EMR is greater than 1.00 but less than or equal to 1.10 | -10 percent |
EMR is greater than 1.10 but less than or equal to 1.20 | -20 percent |
EMR is greater than 1.20 | -40 percent |
Yes | No | |
Employee of the firm completed an OSHA 500 or | +2 percent | 0 percent |
OSHA 502 course in last four years. | ||
Employee of the firm completed Council on | +2 percent | 0 percent |
Certification of Health, Environmental and Safety | ||
Technologists (CCHEST) "Safety Trained Supervisor | ||
in Construction" course. | ||
Employee of the firm completed Associated | +2 percent | 0 percent |
General Contractors of America (AGCA) "Safety | ||
Management Training Course." | ||
The percentage value for the EMR and the percentage value for the safety information shall be added together and this total shall be the safety adjustment. The safety adjustment shall be used as "C" in the calculation of the firm's Project Rating in 19:38B-3.5.
N.J. Admin. Code § 19:38B-3.7