N.J. Admin. Code § 19:38B-3.2

Current through Register Vol. 56, No. 17, September 3, 2024
Section 19:38B-3.2 - Submission of Project Rating Proposal
(a) A firm must submit a Project Rating Proposal and receive a Project Rating from the Authority in order to submit a technical submittal in response to an RFP under this chapter.
(b) The Project Rating Proposal shall be delivered by the firm to the Authority at the hour, date and place specified in the bid advertisement as may be modified by addendum. Project Rating Proposals will be accepted only from firms currently prequalified with the Authority in accordance with N.J.A.C. 19:38A. A firm may not submit a Project Rating Proposal prior to the effective date of the firm's prequalification.
(c) The Authority shall examine the Project Rating Proposal and all documents required to be submitted with the Project Rating Proposal for completeness and conformity with bidding requirements. If the Authority determines that a Project Rating Proposal received for a school facility package must be rejected as nonresponsive, it shall notify the firm in writing of the rejection of its Project Rating Proposal and the reason for the rejection within 10 business days of the receipt of the Project Rating Proposal unless there are circumstances that require additional time.

N.J. Admin. Code § 19:38B-3.2