N.J. Admin. Code § 19:38-3.1

Current through Register Vol. 56, No. 12, June 17, 2024
Section 19:38-3.1 - Contents of the bid
(a) A bid consists of two separate proposals:
1. The first proposal is the Project Rating Proposal, which consists of information regarding the "other factors" as defined in the Act which will be evaluated by the Authority. The Authority will determine a firm's Project Rating based on this Proposal. A firm may not submit a Project Rating Proposal prior to the effective date of the firm's prequalification. If, in the prior 24-month period, a firm has been assigned a Project Rating, the firm may so indicate on the signed Project Rating Proposal submitted for each project and may request that the Authority apply the prior Project Rating to the current bid, provided that the firm certifies that there has been no change regarding safety, prevailing wage record, or its Authority Project Evaluation Record, since the prior Project Rating was assigned.
2. The second proposal is the Price Proposal which shall contain the price the firm bids for the work as well as other information and documents, as required by the contract documents. A firm may not submit a Price Proposal if it has not been assigned a Project Rating.

N.J. Admin. Code § 19:38-3.1

Amended by R.2014 d.001, effective 1/6/2014.
See: 45 N.J.R. 1592(a), 46 N.J.R. 131(a).
In (a)1, substituted "Authority" for "Corporation" throughout, and substituted "Act" for "EFCFA".