N.J. Admin. Code § 19:36-9.1

Current through Register Vol. 56, No. 12, June 17, 2024
Section 19:36-9.1 - Applicability and effect
(a) Notwithstanding any provisions of N.J.A.C. 19:38 to the contrary, the following provisions will apply to the process and consideration of performance evaluations for contracts procured under this chapter.
1. Every design-builder awarded a design build contract procured pursuant to this chapter will be subject to evaluation in accordance with 18A:7G-36. The performance evaluation will consider the design-builder's performance as a contractor in the following categories: quality of work; scheduling; management; cost control and change orders; safety and industrial hygiene; small business goals; and close-out.
2. The design-builder's performance will be evaluated periodically during the progress of the project. The evaluation will be performed by a reviewer with direct involvement in the management or supervision for the project.
3. The design-builder's performance evaluations will be used by the Authority in evaluating and scoring bidders as to their prior experience on Authority projects, in accordance with the provisions of this chapter, N.J.A.C. 19:38, or 19:38B.

N.J. Admin. Code § 19:36-9.1