N.J. Admin. Code § 19:36-3.3

Current through Register Vol. 56, No. 12, June 17, 2024
Section 19:36-3.3 - Design-build information package
(a) A design-build information package shall be prepared by the Authority, using a design professional either on staff of the Authority and/or the bridging architect.
(b) As a prerequisite to the completion of the design-build information package, the schematic design for the school facilities project must have been approved by the SDA school district, the Authority and the Department, in accordance with the requirements of N.J.A.C. 6A:26, and the Department shall have issued the preliminary project report approving the school facilities project, pursuant to 18A:7G-5(h)(2).
(c) The design-build information package may include, but need not be limited to, the following:
1. A description of the school facilities project, including:
i. Building type and size;
ii. Site development requirements, such as, parking and site requirements and playground equipment;
iii. Description of physical relationships between building spaces and between buildings and other site elements; and
iv. Specific architectural style or concept;
2. Educational specifications and schematic design documents for the school facilities project;
3. Performance specifications and prescriptive specifications regarding materials, systems, performance criteria, energy efficiency, life cycle costs and environmental issues;
4. Assignment of responsibility for obtaining required approvals and permits;
5. Engineering, architectural and/or environmental reports (for example, geotechnical evaluations, building evaluations and/or environmental preliminary assessment); and
6. The terms and conditions for the payment of a stipend, if a stipend is offered.

N.J. Admin. Code § 19:36-3.3

Amended by R.2013 d.053, effective 4/1/2013.
See: 44 N.J.R. 1318(a), 45 N.J.R. 752(a).
In (c)6, inserted ", if a stipend is offered".