Section 19:34B-5.4 - Closeout procedures
(a) Closeout shall occur when all applicable administrative actions and all required work have been completed by the school district. This process shall include the steps enumerated below:
1. In the event there are grant proceeds which have not been expended on approved costs, such unexpended grant proceeds shall be released to the Authority and the amount of the grant shall be reduced by the amount of the unexpended proceeds.
2. Any proceeds of school bonds issued by the district for the purposes of funding the local share of the school facilities project which remain unspent upon completion of the school facilities project shall be used by the district to reduce the outstanding principal amount of the school bonds either through redeeming bonds at the earliest call date or applying such proceeds to payment of principal as principal becomes due. In no event shall such proceeds be utilized to pay the interest expense on the school bonds issued for any school facilities project.
3. The district shall refund to the Authority any grant funds spent on any costs which were disallowed by the Authority as not being approved costs. Such refund shall be made within 30 days of the request by the Authority.
4. The district shall remit to the Authority any remaining interest earned pursuant to 19:34B-5.3(b) upon final completion of the school facilities project.
5. If a final audit has not been performed on behalf of the district prior to closeout of the school facilities project, the Authority retains the right to recover any appropriate amount after full consideration of any recommendation on disallowed costs resulting from the final audit.
6. The Authority may require additional information from the district or its consultants and contractors and/or retain any grant amount not disbursed until closeout is completed.