N.J. Admin. Code § 19:3-5.15

Current through Register Vol. 56, No. 11, June 3, 2024
Section 19:3-5.15 - Amendments to redevelopment plan
(a) Amendments to an adopted redevelopment plan, as proposed by the NJMC staff or by any other interested party, may be brought before the Commission by the NJMC staff.
(b) Petitions for amendments to an adopted redevelopment plan shall be submitted in writing. A petition shall include:
1. The full name and address of the petitioner;
2. The block and lot number designation of the properties;
3. A statement indicating why the redevelopment plan should be amended; and
4. Such other information from a specific petitioner as may be deemed necessary by the NJMC staff.
(c) The NJMC staff shall review all petitions for amendments to an adopted redevelopment plan.
(d) If the NJMC staff determines that the petition does not meet the intent and purpose of the redevelopment plan, the petition shall not require further agency action. An appeal from the NJMC staff determination may be made in accordance with 19:4-4.1 9.
(e) If the NJMC staff determines that the petition lacks sufficient information on which to proceed, the petition shall be deemed incomplete. The document shall be returned to the petitioner with an explanation of the deficiencies. The petitioner may address these reasons and resubmit.
(f) Upon receipt of a complete petition, the NJMC staff shall proceed with a public hearing in accordance with 19:4-4.1 7 and the notice requirements of 19:3-5.5.
(g) Subsequent to the public comment period, the NJMC staff shall submit a recommendation to the Commission to either approve, deny, or modify the proposed amendments.
(h) Amendments to the redevelopment plan shall not impact the "in need of redevelopment" designation for the area in question.
(i) The amended redevelopment plan shall supersede all previous redevelopment plans for the area in question.

N.J. Admin. Code § 19:3-5.15