N.J. Admin. Code § 19:31V-1.8

Current through Register Vol. 56, No. 12, June 17, 2024
Section 19:31V-1.8 - Approval letter; incentive award agreement
(a) Upon receipt of a recommendation from the Authority staff on the redevelopment project, the Board shall determine whether or not to approve the application, the maximum amount of tax credits, and the maximum percentage amount of allowed tax credits for its capital investment in a redevelopment project, and promptly notify the applicant, any co-applicant, and the Director of the Division of Taxation of the determination.
1. The Board's award of the tax credits will be subject to conditions subsequent that must be met in order to retain the credits. An approval letter setting forth the conditions subsequent will be sent to the applicant and any co-applicant. Such conditions shall include, but not be limited to, the requirement that the project complies with the Authority's prevailing wage requirements, P.L. 2007, c. 245 (N.J.S.A. 34:1B-5.1) and affirmative action requirements, P.L. 1979, c. 303 (N.J.S.A. 34:1B-5.4), that the project does not violate any environmental law requirements, including, but not limited to, the Flood Hazard Area Control Act Rules, N.J.A.C. 7:13, and the requirement that the minimum environmental and sustainability standards are incorporated into the proposed project. The approval letter shall also provide the requirements necessary for the Authority to execute the incentive award agreement.
2. The approval letter shall require documentation evidencing project financing and planning approvals, including the submittal of executed financing commitments, documents that evidence site control by the developer or an affiliate of the developer, a copy of the site plan approval, and a copy of all required permits and planning and zoning approvals and permits. If a developer is applying as a major cultural institution or to undertake a redevelopment project in which the proposed major cultural institution has an ownership interest, and the developer applied on the basis of contributions and grants, the approval letter shall also require submittal of executed grant and contribution agreements. If the Authority approval included a co-applicant, the required documents shall also include the executed participation agreement between the co-applicant and the developer with a term that extends for the duration of the eligibility period. Absent extenuating circumstances or the Authority's determination, in its sole discretion, the Authority's approval of the tax credits shall expire if the developer or co-applicant, as applicable, does not submit the documentation required in this paragraph within a year after approval of the application.
3. If the terms of the financial commitment in the evidence required by the approval letter are materially different from the projected terms in the application, the Authority may re-evaluate the project financing gap and reduce the size of the incentive award, accordingly.
4. The approval letter shall provide an estimated date of completion and include a requirement for periodic progress reports. If the Authority does not receive a progress report when required, or if the progress report demonstrates unsatisfactory progress, then the Authority, upon consultation with the Agency, and if the Agency has provided financial assistance or awarded tax credits to the redevelopment project, may rescind the incentive award. If the Authority rescinds an incentive award in the same calendar year in which the Authority approved the incentive award, then the Authority may allocate the unused tax credits to another applicant.
(b) Following satisfaction of the requirements for the execution of an incentive award agreement, the Authority shall enter into an incentive award agreement with the developer and any co-applicant. The Chief Executive Officer of the Authority shall negotiate the terms and conditions of the incentive award agreement on behalf of the State. The awarding of tax credits shall be conditioned on the developer's and any co-applicant's compliance with the requirements of the agreement.
(c) The incentive award agreement shall specify and include:
1. A detailed description of the proposed redevelopment project. For a phased project, the incentive award agreement may include an incentive phase agreement for each phase, which shall contain a description of the phase, the expected project cost and total development cost, and the commencement and completion for the respective phase;
2. The maximum amount of project cost and the maximum percentage of the project cost that will be used to calculate the amount of tax credits. If the actual project costs are less than the project cost set forth in the application, the tax credit shall be calculated based on the actual project cost;
3. The duration of the eligibility period;
4. A description of the occupancy permit or other event evidencing project completion that begins the eligibility period;
5. An ongoing requirement to provide the Authority with current personnel information that will enable the Authority to administer the Program;
6. A requirement that the developer shall not cease to operate the redevelopment project during the eligibility period;
7. A method for the developer to certify that it has met the project cost and other eligibility requirements of the Program;
8. A requirement for the developer to provide annual financial statements, as certified by a certified public accountant and accompanied by an unqualified opinion, reporting the project's financial performance;
9. Representations that the developer will comply with the minimum environmental and sustainability standards;
10. Representations that the developer and any co-applicants are in substantial good standing and that the redevelopment project will comply with all applicable laws, including, but not limited to, prevailing wage requirements pursuant to N.J.A.C. 19:31V-1.14(b) and (c), affirmative action requirements pursuant to N.J.A.C. 19:31V-1.14(a), and environmental laws, including, but not limited to, the Flood Hazard Area Control Act Rules, N.J.A.C. 7:13;
11. A provision permitting an audit of evidence and documentation, of the developer and any co-applicant, supporting the certifications pursuant to (f) below, and the annual reports pursuant to N.J.A.C. 19:31V-1.9, as the Authority deems necessary;
12. Reporting requirements pursuant to N.J.A.C. 19:31V-1.9;
13. A provision permitting the Authority to amend the agreement;
14. A provision establishing the conditions pursuant to which the Authority, the developer and any co-applicant, or all parties, may terminate the agreement;
15. Milestones for the redevelopment project, which shall include the estimated date of commencement and completion of the project, and a provision that the Authority, upon consultation with the Agency, if the Agency has provided financial assistance or awarded tax credits to the redevelopment project, may rescind the award of tax credits if a project fails to advance in accordance with the milestones in the incentive award agreement or fails to provide progress reports required pursuant to the approval letter;
16. A provision to verify the financing gap and the developer's updated projected cash flow at the time the developer submits the evidence of the completion of the project pursuant to (f) below, which shall include, but is not limited to, any executed permanent financing commitments. To ensure the protection of taxpayer money, if the Authority determines at project certification that the actual capital financing approach utilized by the project or the updated projected cash flow has resulted in a financing gap that is smaller than the financing gap determined at Board approval, the Authority shall reduce the amount of the tax credit or accept payment from the developer on a pro rata basis. If there is no project financing gap due to the actual capital financing approach utilized by the project or the updated projected cash flow, then the developer shall forfeit the incentive award;
17. A provision requiring that at the end of the seventh year of the eligibility period, the Authority shall evaluate the developer's actual reasonable and appropriate rate of return on investment and compare that actual reasonable and appropriate rate of return on investment to the reasonable and appropriate rate of return at the time of Board approval. If the actual rate of return on investment exceeds the reasonable and appropriate rate of return on investment at the time of Board approval by more than 15 percent, the Authority shall require the developer to pay 20 percent of the amount in excess of the reasonable and appropriate rate of return on investment at time of Board approval. The Authority shall require an escrow account to be held by the Authority until the end of the eligibility period. Following the final year of the eligibility period, the Authority shall determine if the developer's actual rate of return exceeded the reasonable and appropriate rate of return determined at Board approval. If the final actual rate of return does not exceed the reasonable and appropriate rate of return determined at Board approval, the Authority shall release to the developer the escrowed funds. If the actual project final rate of return exceeds the reasonable and appropriate rate of return determined at Board approval, the Authority shall require the developer to pay 20 percent of the amount of the excess, which shall include the funds held in escrow, and such funds shall be deposited in the State General Fund;
18. A provision acknowledging the Authority's right to confirm with the Department of Environmental Protection, the Department of Labor and Workforce Development, and the Department of the Treasury, as set forth at N.J.A.C. 19:31V-1.7(b)1, that the developer, and any co-applicant, is in substantial good standing or has entered into an agreement with the respective department that includes a practical corrective action plan, as applicable;
19. A provision providing that if the developer, and any co-applicant, is not in substantial good standing with the Department of Environmental Protection, the Department of Labor and Workforce Development, and the Department of the Treasury and has not entered into an agreement with the respective department, as set forth at N.J.A.C. 19:31V-1.7(b)1, and after being given written notice thereof and an opportunity to be heard or to contest the determination by the respective department, then the developer and any co-applicant shall forfeit the tax credits in any year in which the developer and any co-applicant is neither in substantial good standing with each department nor has entered into a practical corrective action;
20. A requirement that the developer shall include in all commercial leases or other commercial occupancy agreements and shall require that all subleases or other commercial occupancy agreements applicable to the redevelopment project include, a provision setting forth the requirements at N.J.A.C. 19:31V-1.3(a)9, which provision shall be in a form acceptable to the Authority. A provision that if a commercial tenant, commercial subtenant, or other commercial occupant fails to pay the required prevailing wage rate as set forth at N.J.A.C. 19:31V-1.3(a)9, then the issuance of tax credits to the developer and any co-applicant shall be delayed until such time as documentation demonstrating compliance has been provided to the Commissioner of Labor and Workforce Development, subsequently reviewed and approved by the Commissioner of Labor and Workforce Development, and verified by the Authority;
21. A requirement that the developer shall confirm that each contractor or subcontractor performing work at the redevelopment project: is registered as required by the Public Works Contractor Registration Act, N.J.S.A. 34:11-56.48 et seq.; has not been debarred by the Department of Labor and Workforce Development from engaging in or bidding on Public Works Contracts in the State; and possesses a tax clearance certificate issued by the Division of Taxation in the Department of the Treasury;
22. A requirement for the developer to engage in on-site consultations prior to commencement of construction with the Division of Workplace Safety and Health in the Department of Health;
23. A requirement for the developer of a redevelopment project with newly constructed residential units to comply with the affordability controls;
24. A provision allowing the Authority to extend, in individual cases, the deadline for any annual reporting or project completion certification requirement;
25. Indemnification and insurance requirements from the developer and any co-applicant;
26. Events that would trigger forfeiture, reduction, or recapture of the tax credits, including, but not limited to, provisions in this subchapter; and
27. Default and remedies, including, but not limited to, a default if a developer or any co-applicant made a material misrepresentation on its application, provided that the incentive award agreement shall not allow the Authority to declare a cross-default when the developer of a redevelopment project, including any business affiliate of the developer or any other entity with common principals as the developer, is in default with any other assistance program administered by the Authority.
(d) The Authority shall not enter into an incentive award agreement for a redevelopment project that includes at least one retail establishment that will have more than 10 full-time employees, at least one distribution center that will have more than 20 full-time employees, or at least one hospitality establishment that will have more than 10 full-time employees, unless the incentive award agreement includes a precondition that any business that serves as the owner or operator of the retail establishment, distribution center, or hospitality establishment enters into a labor harmony agreement with a labor organization or cooperating labor organizations that represent retail or distribution center employees in the State. A labor harmony agreement shall be required only if the State has a proprietary interest in the redevelopment project and shall remain in effect for as long as the State acts as a market participant in the redevelopment project. The Authority may enter into an incentive award agreement with a developer and any co-applicants without the labor harmony agreement required pursuant to this subsection, if the Authority determines that the redevelopment project would not be able to go forward if a labor harmony agreement is required. The Authority shall support the determination by a written finding, which provides the specific basis for the determination.
(e) Except as set forth at (e)1 below, for a redevelopment project whose total project cost equals or exceeds $ 10 million, in addition to the incentive award agreement, the developer and any co-applicant that is responsible or required to provide services pursuant to the community benefits agreement shall execute a community benefits agreement in accordance with N.J.S.A. 34:1B-328.f, as prescribed below.
1. A developer shall not be required to enter into a community benefits agreement pursuant to this subsection if:
i. The developer submits to the Authority a copy of either the developer's approval letter from the Authority or a redevelopment agreement applicable to the redevelopment project, provided that the approval letter or redevelopment agreement is certified by the municipality in which the redevelopment project is located, and includes provisions that meet or exceed the standards required for a community benefits agreement in this subsection, as determined by the Chief Executive Officer;
ii. The developer submits to the Authority:
(1) A resolution adopted by the governing body of the municipality in which the redevelopment project is located, which states and explains the governing body's reasons and determined that the redevelopment project will provide economic and social benefits to the community that fulfill the purposes at N.J.S.A. 34:1B-328.f and this subsection and, thus, rendering a separate community benefit agreement unnecessary; and
(2) Documentation that the resolution was adopted after at least one public hearing at which the governing body provided an opportunity for residents, community groups, and other stakeholders to testify; or
iii. the project is a residential project that is located in a government-restricted municipality, and in which 100 percent of the residential units constructed in the residential project are reserved for occupancy by low- and moderate-income households.
2. The developer shall enter into a community benefits agreement with the Authority and the chief executive of the municipality or, if requested by the chief executive of the municipality, the chief executive of the county, in which the redevelopment project is located. If the municipality requests the county to enter into the agreement, the chief executive of the municipality must submit to the Authority a signed letter notifying the Authority that the municipality has made the request. The Authority shall not participate in negotiations between the developer and the municipality or county; however, the Authority shall review the agreement prior to the execution of the agreement to determine compliance with the requirements of this subsection including, but not limited to, a provision for mediation as required pursuant to (e)7ii below. The agreement may include, but shall not be limited to, requirements for training, employment, and youth development and free services to underserved communities in and around the community in which the redevelopment project is located, as well as any other Program element, on the project site or in the host community, intended to improve community health, safety, access to opportunity, recreational opportunity, environmental resilience and environmental quality, quality of life, or other locally-prioritized community benefit.
3. The community benefits agreement or redevelopment agreement shall include a list of contributions by the developer; the monetary equivalent for any non-monetary contribution; an event of default, if the developer forfeits tax credits pursuant to N.J.A.C. 19:31V-1.10(e)2 in two successive years; and the date by which the community advisory committee must submit its annual report pursuant to (e)7 below.
4. The developer and the municipality or county shall have six months, with two three-month extensions, after Authority Board approval of the developer's application, to enter into a community benefits agreement, the redevelopment agreement, or approve the resolution and submit such agreement or resolution to the Authority. Submission of such community benefits agreement, redevelopment agreement, or resolution is a condition to entering into an incentive award agreement.
5. Prior to entering a community benefits agreement or a redevelopment agreement, the governing body of the municipality or, if the county is executing the agreement, the governing body of the county, in which the redevelopment project is located shall hold at least one public hearing subject to the Senator Byron M. Baer Open Public Meetings Act, N.J.S.A. 10:4-6 et seq., at which the chief executive, or designee from the chief executive's department or office, shall hear testimony from residents, community groups, and other stakeholders on the needs of the community that the agreement should address. The chief executive, or designee, shall provide a record, including hearing minutes, satisfactory to the Authority, which shall be an exhibit to the community benefits agreement.
6. The community benefits agreement or redevelopment agreement shall provide for the creation of a community advisory committee to oversee the implementation of the agreement, monitor successes, and ensure compliance with the terms of the agreement, as follows:
i. The community advisory committee created pursuant to this paragraph shall be comprised of representatives from diverse community groups and residents of the municipality or, if the county is executing the agreement, community groups and residents of the county in which the redevelopment project is located.
ii. The chief executive of the municipality or, if the county is executing the agreement, the chief executive of the county shall appoint the members of the community advisory committee, which shall consist of not less than three members.
iii. For new construction or substantial rehabilitation projects, the community advisory committee shall have at least one representative from the business community in the zip code in which the redevelopment project is located, at least one representative from a community group, and at least one resident from the zip code in which the redevelopment project is located. There shall be no more than one municipal or county employee on the community advisory committee.
iv. For all other projects, the community advisory committee shall be determined by the chief executive of the municipality, or if the county is executing the agreement, the chief executive of the county, without regard to the criteria listed at (e)6iii above.
v. Community advisory committee members shall be required to sign a letter certifying that they have no financial or other interested relationship with the developer and any co-applicant. The certifications shall be submitted to the Authority by the developer or the municipality, or if the county is executing the agreement, the county.
vi. Any report or action shall be approved by a majority of the members of the community advisory committee.
7. The community advisory committee shall produce an annual report, including an evaluation of whether the developer is in compliance with the terms of the community benefits agreement or the redevelopment agreement:
i. If the report from the community advisory committee and the certification from the developer pursuant to N.J.A.C. 19:31V-1.9(b)1 both indicate that the developer is in compliance with the community benefits agreement, then the developer shall be in compliance with the community benefits agreement. Absent extenuating circumstances, and the written approval of the Authority, if the community advisory committee does not timely submit the annual report, then the determination of compliance of the developer shall be based on the certification from the developer pursuant to N.J.A.C. 19:31V-1.9(b)1.
ii. If the report from the community advisory committee indicates that the developer is not in compliance with the terms of the community benefits agreement, the Authority shall serve as, or identify, a mediator. The community advisory committee, municipality, or county, as applicable, and the developer shall enter into non-binding mediation to seek resolution or mutually agreeable amendments to the community benefits agreement within 60 days of the notice from the Authority of the person who will serve as a mediator. Thereafter, the results of the mediation shall be reported to the Authority.
iii. If a resolution is not able to be achieved through mediation, a hearing officer will be assigned by the Authority. The hearing officer shall perform a review of the written record and may require an in-person hearing. The hearing officer has sole discretion to determine if an in-person hearing is necessary to reach an informed decision on the appeal. Following completion of the record review and in-person hearing, as applicable, the hearing officer shall issue a written report to the Chief Executive Officer containing his or her finding(s) and recommendation(s). The hearing officer's report shall be advisory in nature. The developer, municipality or county, and the community advisory committee shall receive a copy of the written report of the hearing officer and shall have the opportunity to file written comments and exceptions to the hearing officer's report within five business days from receipt of such report. The Chief Executive Officer shall consider the hearing officer's report and any timely submitted written comments and exceptions. Based on that review, the Chief Executive Officer shall make a determination of compliance or non-compliance. The process described in this subsection is not a contested case subject to the requirements of the Administrative Procedure Act, N.J.S.A. 52:14B-1 et seq., and 52:14F-1 et seq., and the Uniform Administrative Procedure Rules, N.J.A.C. 1:1.
8. The sum of costs for benefits and services provided pursuant to the community benefits agreement or the redevelopment agreement included as soft costs or to determine cash flow shall not exceed five percent of project cost. For purposes of this paragraph, costs for benefits and services incurred during the eligibility period shall be discounted to present value.
(f) A developer shall submit, prior to the issuance of tax credits pursuant to the incentive award agreement, but no later than six months following project completion, satisfactory evidence of the completion of the redevelopment project and satisfaction of the Program eligibility requirements, which shall include, but not be limited to, the documents in this subsection. The Authority may provide any information in the annual report to the Agency for any redevelopment project if the Agency has provided financial assistance or awarded tax credits to the redevelopment project.
1. Evidence of a temporary certificate of occupancy or other event evidencing project completion that begins the eligibility period indicated in the incentive award agreement;
2. A certification by a qualified independent certified public accountant of the actual project costs. The certification shall be made pursuant to an "agreed upon procedures" letter acceptable to the Authority. If the project cost is reduced below the relevant minimum project cost for eligibility, the redevelopment project shall no longer be eligible. If the project cost in the certification is less than the project cost in the approval of the application, the Authority may re-evaluate the net positive economic benefit and reduce the size of the tax credits accordingly. The Authority shall qualify certified public accountants and provide to the developer the list of qualified certified public accountants; provided, however, the developer may select a certified public accountant that is independent to the developer and any co-applicant and not on the Authority's list of qualified certified public accountants for purposes of the project cost certification, if the developer demonstrates an extenuating circumstance prohibiting the developer from retaining a qualified certified public accountant. Such circumstances include, but are not limited to, the unavailability of any of the qualified certified public accountants to timely complete the certification or none of the qualified certified public accountants are independent to the developer;
3. A floor plan identifying the actual and proposed uses and square foot of gross leasable area for each such use and, if the redevelopment project comprises multiple buildings, a site plan. For a redevelopment project with eligibility requirements on size or uses, including, but not limited to, predominance of commercial, residential, or film production uses, evidence that the project satisfies all such requirements. For a redevelopment project in which any commercial tenant, commercial subtenant, or other commercial occupant is the party to the contract to perform building services work as set forth at N.J.A.C. 19:31V-1.3(a)9, the floor plan, or site plan, shall identify all such tenants, the premise occupied by each such tenant, and the size of the space occupied by such tenant;
4. A certification indicating whether or not the developer is aware of any condition, event, or act that would cause the developer or any co-applicant not to be in compliance with the approval, the Act, or this subchapter;
5. A letter from the Agency to the developer with a copy to the Authority confirming compliance with the affordability controls;
6. A certification from a licensed engineer that the redevelopment project has adhered in all material respects to the plan submitted by the developer describing how the developer would satisfy the minimum environmental and sustainability standards;
7. Any permanent financing commitments executed as of the date of the submission of the documents in this subsection and an updated project pro forma;
8. A certification by the chief executive officer or equivalent officer of the developer that the information provided pursuant to this subsection is true pursuant to the penalty of perjury. Claims, records, or statements submitted by a developer to the Authority in order to receive tax credits shall not be considered claims, records, or statements made in connection with State tax laws; and
9. If the Authority approval included a co-applicant, a certification that the participation agreement between the developer and the co-applicant remains in effect and is not in default.
(g) A developer shall forfeit the credit amount for any tax period for which the developer's documentation remains uncertified by the Authority as of the date for certification indicated in the incentive award agreement, although credit amounts for the remainder of the years of the eligibility period shall remain available to the developer.
(h) Once the Authority accepts the documentation required at (f) above and the Authority determines that all eligibility requirements and other required conditions have been met, within 90 days of the Authority's acceptance of the documentation and evidence satisfactory to the Authority, the Authority shall notify the developer and notify the Director. The developer shall receive its tax credit certificate that will be based on the information submitted in the certification pursuant to (f) above, provided it shall not exceed the maximum amount determined by the Board pursuant to N.J.A.C. 19:31V-1.7(e), (f), and (g). The use of the tax credit certificate shall be subject to the receipt of an annual certificate of compliance issued by the Authority.
(i) At, or before, the date of certification, any modification to the redevelopment project as approved by the Board, including, but not limited to, a reduction in the amount of the project cost, or square feet, shall require review and approval by the Authority to determine that the redevelopment project, as modified, does not undermine the basis for the tax credit award approved.

N.J. Admin. Code § 19:31V-1.8

Recodified from 19:31-23A.8 56 N.J.R. 807(a), effective 5/6/2024