N.J. Admin. Code § 16:47-10.4

Current through Register Vol. 56, No. 23, December 2, 2024
Section 16:47-10.4 - Permit conditions
(a) Permit conditions may include, but not be limited to, the following:
1. A developer agreement pursuant to N.J.A.C. 16:47-10.5;
2. A fair share agreement pursuant to N.J.A.C. 16:47-10.6;
3. A traffic signal electrical agreement as described in N.J.A.C. 16:47 Appendix G;
4. Right-of-way dedication pursuant to N.J.A.C. 16:47-10.7;
5. Those site-specific terms and conditions deemed necessary and convenient;
6. A restoration bond and a maintenance bond or certified checks in an amount sufficient to guarantee completion of the work or insure proper restoration and maintenance of the area disturbed by the lot or site owner. If it becomes necessary for Department staff or contractors to make repairs, for any reason, the cost of such work shall be borne by the lot or site owner;
7. A statement that the trip expansion limits have been reduced or eliminated for the lot or site;
8. Provisions for indemnification of the State and its employees and officials. Examples of these provisions shall be available upon request from the appropriate permits unit;
9. A requirement that the lot or site owner shall obtain and provide the Department with copies of any other agency approvals required for work within either existing or proposed State highway ROW;
10. If final plans are not approved at the time of permit issuance, a provision that no construction within the State highway ROW can occur until final plans are approved by the Department;
11. A provision that at least two weeks prior to the start of construction, the lot or site owner shall notify the Department of the anticipated start date, so that a preconstruction conference can be scheduled;
12. A provision stating that construction cannot begin until the lot or site owner obtains a confirmation number from the One-Call Damage Prevention System, in accordance with N.J.S.A. 48:2-83, and provides the confirmation number to the Department office issuing the access permit. The lot or site owner shall provide this confirmation number at least 72 hours before starting construction work. The lot or site owner shall also provide confirmation to the Department's Operations Permit Office that the Department's Bureau of Intelligent Transportation Systems has been contacted a minimum of 10 business days prior to the start of construction for a determination of any fiber optic cable or conduit facilities within the area of proposed construction, pursuant to the provisions of N.J.A.C. 16:41;
13. A provision that the lot or site owner shall notify the Department's Operations Permit Office at least 72 hours prior to the start of construction, in order that the Department may have a representative at the site; and
14. A provision that if the ownership of the lot or site changes prior to final inspection, the Department must be notified of the change in ownership and who is responsible for completing the work.

N.J. Admin. Code § 16:47-10.4

Adopted by 50 N.J.R. 1534(b), effective 7/16/2018