N.H. Admin. Code § Puc 909.02

Current through Register No. 44, October 31, 2024
Section Puc 909.02 - Applicability
(a)Puc 909.01 through Puc 909.15 shall apply to customer-generators who elect to become hosts, to group members, and to distribution utilities that serve hosts and group members.
(b) Large customer-generators subject to the alternative net metering tariff that do not consume behind-the-meter at least 20 percent of the actual or estimated annual electricity production from their facilities shall register as group hosts pursuant to this part or they shall be ineligible to net meter.
(c)Puc 909.12 applies to customer-generators who or which register or re-register as a host on or after July 1, 2019 and elect to receive on-bill credits.
(d)Puc 909.13 applies to customer-generators who or which meet the requirements specified therein to register as a low-moderate income community solar project.

N.H. Admin. Code § Puc 909.02

Derived from Volume XL Number 33, Filed August 13, 2020, Proposed by #13080, Effective 9/14/2020, Expires 9/14/2030