N.H. Admin. Code § Puc 904.01

Current through Register No. 50, December 12, 2024
Section Puc 904.01 - Pre-Application Review
(a) Before purchasing or installing net energy metering equipment, a customer-generator may request that the distribution utility informally review the proposed project and provide information on:
(1) Whether the customer-generator's facility and electric distribution system interface, in the opinion of the distribution utility, is likely to comply with the requirements of Puc 900; and
(2) Whether the customer-generator is in an area or service location which is likely to require any upgrade or study.
(b) At the pre-application stage, the distribution utility shall provide the customer-generator its best evaluation, given the information it has available, but shall not be required to conduct a study or extensive review of the proposed project.

N.H. Admin. Code § Puc 904.01

#2050, eff 6-13-82; ss by #2404, eff 6-28-83; ss by #2912, eff 11-26-84; EXPIRED 11-26-90

New. INTERIM #5921, eff 11-7-94, EXPIRED 3-7-95

New. #7424, eff 1-12-01; ss by #9353, INTERIM, eff 1-12-09, EXPIRED: 7-11-09

New. #9515, eff 7-18-09; ss by #9998, eff 9-20-11

Amended by Volume XL Number 33, Filed August 13, 2020, Proposed by #13080, Effective 9/14/2020, Expires 9/14/2030