N.H. Admin. Code § Puc 409.05

Current through Register No. 45, November 7, 2024
Section Puc 409.05 - Form T-5 Facility Disruption Report

The "Facility Disruption Report" required by Puc 406.03(d), shall include:

(a) Utility filing information;
(b) The date of the report;
(c) The date and time of the outage;
(d) The location of the outage;
(e) Whether an entire exchange was affected, to the best knowledge of the ELEC or ILEC;
(f) The number of affected access lines;
(g) The cause of the outage;
(h) The date and time service was restored;
(i) The name of the person contacted at the commission; and
(j) The date and time the commission was contacted.

N.H. Admin. Code § Puc 409.05

#10542, eff 3-12-14 (See Revision Note #2 at chapter heading for Puc 400)

Ss by #10542, eff 3/12/2014 (See Revision Note #2 at chapter heading for Puc 400).