Section Puc 2005.03 - Suspension of Registration of CEPS or Aggregator
(a) If the commission finds, after notice and an opportunity to be heard and after consideration of the factors described in Puc 2005.05, that a sanctionable event has occurred with respect to a CEPS or aggregator and that the interests of customers of the CEPS or aggregator would not be harmed by such action, the commission shall suspend the registration of the CEPS or aggregator for a specified period of time not to exceed the remaining term of the CEPS's or aggregator's current registration under Puc 2003.
(b) Upon the issuance by the commission of an order under (a) above, the registration of the CEPS or aggregator shall be suspended and the CEPS or aggregator shall not provide service, either directly or indirectly, to any customers in the state with respect to the supply of electricity or the procurement of such supply during the specified period of suspension.
(c) The CEPS or aggregator subject to a suspension order issued under (a) above shall make arrangements for all of its customer accounts to be transferred and provide prior written notice to customers of such transfers in compliance with the provisions of such order and the requirements of this chapter. The CEPS or aggregator shall provide the commission with written confirmation and supporting evidence that it has complied with the foregoing requirements.

N.H. Admin. Code § Puc 2005.03

Derived From Volume XXXVII Number 37, Filed September 14, 2017, Proposed by #12372, Effective 11/1/2017, Expires 11/1/2027.