N.H. Admin. Code § Puc 1606.02

Current through Register No. 50, December 12, 2024
Section Puc 1606.02 - Filing Requirements
(a) Each utility shall comply with filing requirements relating to special contracts, as follows:
(1) Any utility which proposes a special contract shall file the terms of the proposed agreement at least 30 days before its proposed effective date;
(2) If both parties to the proposed contract are utilities, the seller of utility services shall be responsible for filing;
(3) An authorized official from the utility shall sign the special contract filing;
(4) A utility shall file a special contract filing, including letters of transmittal and all supportive documentation, as follows:
a. With the commission, notwithstanding the requirements of Puc 202.07, 3 copies;
b. With the office of consumer advocate, one hard copy; and
c. Pursuant to Puc 203.03, electronically file each document, to the extent technologically feasible, in a format compatible with the computer system of the commission.
(5) In the case of special contracts for electric service, the utility shall file a written statement of the customer to the special contract confirming that the tariffed rate will not serve its needs.
(b) A utility shall include as part of any proposed special contract filing, a statement describing the special circumstances that justify the departure from its existing tariff.

N.H. Admin. Code § Puc 1606.02

#6573, eff 9-10-97; ss and moved by #8428, eff 9-10-05 (from Puc 1606.03 ); ss by #10535, eff 3-4-14