(a) A utility shall include page designations on each revised page of a tariff revision according to the requirements of this section.(b) A utility shall designate in the upper right hand corner on each revised page, on separate lines, designations indicating:(1) The revision number of this page and the page number; and(2) The revision which this revision supersedes, whether original, first, second or so on, and page number.(c) The designation required by (b) above shall appear as in the illustration below: Figure 16.3.2 Page Designation
1st Revised Page 3
Superseding Original Page 3
(d) When a new tariff is filed, replacing an existing tariff, the utility shall include designations on separate lines in the upper left hand corner of the page, as follows: (1) The title page of the new tariff shall show:a. The number of the new tariff and the utility type; andb. The number of the superseded tariff and the utility type; and(2) Each page other than the title page shall show the number of the new tariff and the utility type.(e) The designations required by (d)(1) above, to be shown on the title page of a new tariff, shall appear as in the illustration below: Figure 16.3.3 Title Page Designation
NHPUC No. 2 - Electricity
Superseding NHPUC No. 1 - Electricity
(f) When tariff changes require that an additional page or pages be inserted, a utility shall use the same page number with a letter or numerical suffix for all additional pages.(g) The utility shall include a designation on each added page, in the upper right hand corner of the page, which states the page number followed by a letter or numerical suffix.(h) The designation as required by (g) above shall appear as in the illustration below: Figure 16.3.4 Page Designation on Each Added Page
Original Page 2-A
or
Original Page 2.1
(i) When a page is to be deleted, a utility shall file a canceling page with a notation as to where the information can be found thereafter or stating that the information has been deleted, as applicable.(j) When a proposed tariff revision is suspended by the commission before becoming effective, the utility shall include designations, in the upper right hand corner and on separate lines of each page affected, as follows: (1) The number of the page revision when single tariff pages are suspended or the number of the tariff when a whole tariff is suspended, and the page number;(2) A statement that the page or whole tariff is "Issued in lieu of"; and(3) The number of the page revision or number of the whole tariff, as applicable, and the page number.(k) The designations required by (j) above, the first for a suspended tariff page revision, and the second for a suspended whole tariff, shall appear as in the illustration below: Figure 16.3.5 Page Designation for Suspensions
3rd Revised Page 2
Issued in lieu of
2nd Revised Page 2
or
NHPUC No. 4
Issued in lieu of
NHPUC No. 3
(l) When a proposed tariff revision is suspended by the commission before becoming effective, its number shall not be reused.(m) When the commission approves a complete new tariff, the utility shall file a title page with the following information displayed at the bottom of the page:(1) A statement, which shall include the information required by (2) through (4) below, that the tariff is "Authorized by NHPUC Order No.in Docket No.__, dated __.";(2) The order number which approves the tariff;(3) The commission docket number of the case; and(4) The date of the order approving the tariff.(n) A utility shall designate on the title page the next consecutive tariff number, the superseded tariff number and the type of utility service.(o) When the commission approves revised tariff pages to be inserted within the existing tariff, the utility shall file each revised page, bearing the notation as described in (m) (1) above.N.H. Admin. Code § Puc 1603.06
#2011, eff 5-4-82; ss by #2912, eff 11-26-84; ss by #5006, eff 11-26-90; ss by #6365, INTERIM, eff 11-18-96, EXPIRED: 3-18-97
New. #6573, eff 9-10-97; ss #8428, eff 9-10-05; ss by #10535, eff 3-4-14