Current through Register No. 50, December 12, 2024
Section He-Hea 301.13 - Change of Scope(a) Pursuant to RSA 151-C:12, IV-a, the board shall require an applicant for a CON to file for a change of project scope if: (1) The total project cost will exceed the CON approved amount by more than 15% plus inflation;(2) The financing method of the application will differ due to cost overruns that exceed 15% plus inflation;(3) The identity of the applicant has changed;(4) The services, programs, or equipment identified in the CON application will be located in a service area or site different from that named in the application; or(5) Services, programs or equipment are being proposed to be added or omitted from those previously identified in the CON application.(b) Applicants shall file a change of scope using the form as described in He-Hea 301.14.(c) A change of scope application may be filed at anytime after the CON has been approved.(d) A waiver of any change of scope requirements shall be approved if the services, programs or equipment to be added or omitted are not significant because they will not result in: (1) A change to the approved CON amount;(2) The introduction of a new services, program or equipment to the service area; or(3) A reduction in accessibility from that anticipated in the original CON application.(e) The board shall make its determination for either a change of scope or a waiver of such under (d) above during an adjudicative proceeding pursuant to He-Hea 208.01 and issue an order supporting that determination pursuant to He-Hea 214.03(b).N.H. Admin. Code § He-Hea 301.13
#7139, eff 11-23-99, EXPIRED: 11-23-07
New. #9075-B, eff 1-24-08
Amended byVolume XXXIV Number 50, Filed December 11, 2014, Proposed by #10723, Effective 11/22/2014, Expires11/22/2024.Amended by Volume XXXVI Number 19, Filed May 12, 2016, Proposed by #11081-B, Effective 4/23/2016, Expires 4/23/2026.