N.H. Code Admin. R. Env-Wt 521.04

Current through Register No. 25, June 20, 2024
Section Env-Wt 521.04 - Utility Project Application Requirements

The project-specific information required by Env-Wt 310.01(c)(1) or Env-Wt 311.03(b)(11), as applicable, for a utility project shall be as follows:

(a) A plan showing the following:
(1) The extent and location of all wetlands and watercourses within the project area;
(2) A wetland delineation, functional assessment, and impact analysis in accordance with Env-Wt 300;
(3) The location of any existing utility corridors and facilities;
(4) The location of the proposed utility corridors and facilities; and
(5) The location of any proposed impacts, crossings, construction areas, and clearings;
(b) A recent aerial photograph of the project area overlain by the items specified in (a)(1), above;
(c) A description of the methods, techniques, vehicles, and equipment proposed to access and conduct the project;
(d) An invasive species control plan;
(e) A description of measures proposed to minimize and avoid impacts to wetlands and surface waters;
(f) A construction sequence plan describing measures proposed to minimize impacts to water quality, impacts to nesting and breeding species, and to prevent compaction of wetlands soils; and
(g) The locations of staging areas, off right-of-way access roads, temporary access roads, and new station locations.

N.H. Code Admin. R. Env-Wt 521.04

Derived from Volume XXXIX Number 28, Filed July 11, 2019, Proposed by #12805, Effective 12/15/2019, Expires 12/15/2029.
Amended by Volume XL Number 46, Filed November 12, 2020, Proposed by #13124, Effective 10/23/2020, Expires 10/23/2030.