Current through Register No. 45, November 7, 2024
Section Env-Wt 521.02 - Utility Project Criteria for Approval(a) Work may be done under utility SPN only if: (1) The project meets the minimum impact criteria in Env-Wt 521.06(a);(2) The project has only: a. Temporary impacts associated with inspections, maintenance, and repair of existing utility assets and rights of way; andb. Less than 3,000 SF of permanent impacts for replacement of utility assets; and(3) The project proponent agrees to follow the Utility BMPs, available as noted in Appendix B.(b) Work shall not be done under a utility SPN if the project:(1) Establishes one or more new permanent access roads in jurisdictional areas;(2) Installs one or more permanent crossings of streams or wetlands, or both;(3) Constructs one or more new utility corridors or rights-of-way;(4) Installs new utility assets within existing utility corridors or rights-of-way;(5) Does not meet the standard conditions in Env-Wt 307; or(6) Otherwise exceeds the minimum impact criteria.N.H. Admin. Code § Env-Wt 521.02
Derived from Volume XXXIX Number 28, Filed July 11, 2019, Proposed by #12805, Effective 12/15/2019, Expires 12/15/2029.