N.H. Code Admin. R. Env-Wt 308.07

Current through Register No. 25, June 20, 2024
Section Env-Wt 308.07 - Post-Notification Requirements for SPNs other than Utility Project SPNs
(a) Prior to commencing the work covered by the SPN, the person responsible for a project other than a utility project shall post at the site a copy of the SPN posted by the department on its web site or provided by the department pursuant to Env-Wt 308.05(d)(2).
(b) Within 10 days following completion of the work covered by an SPN other than a utility project, the person responsible for the project shall submit to the department confirmation of completion of the project, either by paper copy or electronically.

N.H. Code Admin. R. Env-Wt 308.07

Derived from Volume XXXIX Number 28, Filed July 11, 2019, Proposed by #12803, Effective 12/15/2019, Expires 12/15/2029 (See Revision Notes #1, #2, and #3 at chapter heading for Env-Wt 300).
Amended by Volume XL Number 2, Filed January 9, 2020, Proposed by #12954, Effective 12/24/2019, Expires 12/24/2029.