Section Env-Wt 308.07 - Post-Notification Requirements for SPNs other than Utility Project SPNs
(a) Prior to commencing the work covered by the SPN, the person responsible for a project other than a utility project shall post at the site a copy of the SPN posted by the department on its web site or provided by the department pursuant to Env-Wt 308.05(d)(2).
(b) Within 10 days following completion of the work covered by an SPN other than a utility project, the person responsible for the project shall submit to the department confirmation of completion of the project, either by paper copy or electronically.