N.H. Code Admin. R. Env-Ws 373.27

Current through Register No. 25, June 20, 2024
Section Env-Ws 373.27 - Final Inspection
(a) Upon completion of the construction of a non-community water system, but before any service is offered, the department shall conduct a sanitary survey, or inspection, of the water system. This inspection shall be performed within 5 working days after notification by the owner of the proposed water system that construction, including all required testing, is complete. The water system shall not be approved for any service unless this inspection is completed.
(b) The proposed operator for a new NTNCwater system shall:
(1) Have taken or arranged to take the operator certification exam as required under Env-Ws 367; and
(2) Be in attendance at the inspection required under (a), above .

N.H. Code Admin. R. Env-Ws 373.27

(See Revision Note at chapter heading for Env-Ws 300); ss by #8499, eff 11-30-05