N.H. Code Admin. R. Env-Wr 507.01

Current through Register No. 25, June 20, 2024
Section Env-Wr 507.01 - Notification Test
(a) The owner shall conduct a test of the emergency communication network within one month of approval of the EAP and every 2 years thereafter for a high hazard dam and every 4 years thereafter for a significant hazard dam.
(b) The test shall consist of the owner making the primary contact as shown on the flow-chart and indicating that a required test of the EAP is being conducted.
(c) The owner shall request each individual or agency contacted during the test to execute its duties relative to the notification flow-chart, complete the checklists, and return the checklists to the owner.
(d) Within 30 days of conducting the test, the owner shall inform the department of the results of the test, indicating the time it took each individual and agency to make their notifications and whether miscommunications occurred.
(e) The owner shall provide records of communication for each individual and agency, including time of contact and person contacted, if the notifications were not made within a 15-minute time period.

N.H. Code Admin. R. Env-Wr 507.01

#8414, eff 8-20-05; ss by #10510, eff 1-22-14