If the dam will be a low hazard, significant hazard, or high hazard structure, the owner shall submit:
(a) Plans and specifications which shall, at a minimum, include the following: (2) Scaled cross-sectional view of dam through the outlet, showing elevations of inlet and outlet, watertight connections, embankment material;(3) Design of and cover treatment for embankment slopes;(4) Gradation analysis for all soils to be used during construction;(5) Compaction specifications in accordance with Env-Wr 403.02(d) and (e);(6) Construction sequence; and(7) For reconstruction, the plans shall be of sufficient detail to show the location of the proposed work in relation to the entire dam; and(b) A written operation and maintenance plan, which: (1) Describes the seasonal control of impoundment levels;(2) Describes regular maintenance activities; and(3) Includes the name(s) and address(es) of the dam monitor(s).N.H. Admin. Code § Env-Wr 402.06
#8414, eff 8-20-05; ss by #10510, eff 1-22-14