N.H. Admin. Code § Env-Wq 510.03

Current through Register No. 44, October 31, 2024
Section Env-Wq 510.03 - Department Review of Contract Documents
(a) The department shall review the contract documents submitted pursuant to Env-Wq 510.02 within 60 days of receipt.
(b) The department shall approve the contract documents if they:
(1) Meet the requirements stated in Env-Wq 510.02(c);
(2) Are consistent with all applicable state and federal requirements; and
(3) Are consistent with the report submitted pursuant to Env-Wq 506.05(a) or (b), as applicable.
(c) After the contract documents are approved, no changes to the contract documents shall be made unless the recipient obtains prior approval from the department pursuant to Env-Wq 510.06(d).
(d) After the contract documents are approved, no increases in project cost or scope shall be made unless the recipient obtains prior approval from the department pursuant to Env-Wq 510.06(e).
(e) Approval of the contract documents shall not relieve the applicant of any liabilities or responsibilities with respect to the design, construction, operation, or performance of the project.

N.H. Admin. Code § Env-Wq 510.03

(See Revision Note #2 at chapter heading for Env-Wq 500) #9394, INTERIM, eff 3-1-09, EXPIRES: 8-28-09; ss by #9531, eff 8-26-09

Amended by Volume XXXV Number 49, Filed December 10, 2015, Proposed by #10984, Effective 12/1/2015, Expires12/1/2025.
Amended by Number 2, Filed January 12, 2023, Proposed by #13511, Effective 12/20/2022, Expires 12/20/2032.