Section Env-Wq 1905.07 - Implementation Schedule
(a) Each individual water conservation plan, water use plan, and dam management plan shall include an implementation schedule establishing the timeframes within which an affected water user or affected dam owner shall complete any approvals, plans, property or equipment acquisitions, construction, or other activities necessary to perform the ongoing operational requirements in the plan.
(b) Subject to Env-Wq 1906.04, requirements or activities specified in an implementation schedule shall be completed within 5 years after adoption of the water management plan.
(c) Any affected water users or affected dam owners with an implementation schedule longer than 3 years shall make periodic progress reports to the department beginning the year after the water management plan is adopted, as follows:
(1) Progress reports shall be submitted to the department annually on or before the adoption date of the water management plan;
(2) If the implementation schedule is longer than 4 years, or if implementation of a shorter schedule is not completed within 4 years, an affected water user or affected dam owner shall submit an additional written progress report to the department no later than 4.5 years after the adoption of the water management plan; and
(3) A progress report shall include:
a. Identification of the facility, its address, the authorized person submitting the report and that person's contact information;
b. Identification of the incomplete approvals, plans, property or equipment acquisitions, construction, or other requirements or activities necessary to conduct the operational requirements of the water management plan;
c. A description of progress made in the previous year on approvals, plans, property or equipment acquisitions, construction, or other requirements or activities necessary to conduct the operational requirements, including those that were completed;
d. For approvals, plans, property or equipment acquisitions, construction, or other activities necessary to conduct the operational requirements that have not been completed in accordance with the implementation schedule, a supplementary schedule proposing revised timeframes within which such requirements or activities in the plan shall be completed; and
e. The signature of the authorized representative of the facility submitting the report.
(d) Any affected water users or affected dam owners with implementation schedules shorter than 3 years who have not met their implementation schedule goals after three years shall make periodic progress reports as specified in (c), above.

N.H. Code Admin. R. Env-Wq 1905.07

Derived From Volume XXXIX Number 02, Filed January 10, 2019, Proposed by #12695, Effective 12/22/2018, Expires 12/22/2028.