N.H. Admin. Code § Env-Sw 1104.06

Current through Register No. 37, September 12, 2024
Section Env-Sw 1104.06 - Project Engineer and Resident Engineer

A standard permit facility, emergency permit facility not exempt pursuant to Env-Sw 313.02(b) and research and development permit facility not exempt pursuant to Env-Sw 312.02(b), shall comply with the following requirements:

(a) The permittee shall designate a project engineer to:
(1) Administer the technical aspects of the construction contract; and
(2) Provide technical coordination of the design, permitting, and construction issues;
(b) The project engineer shall:
(1) Be a qualified professional engineer;
(2) Administer all construction contracts;
(3) Approve all construction contract change orders;
(4) Monitor all inspections and testing;
(5) Provide statements and reports as required by Env-Sw 1104.05, Env-Sw 1104, and Env-Sw 1105.02;
(6) Maintain facility construction records during the construction period;
(7) Monitor all construction activities to ensure compliance with the permit, specifically including the approved design plans and specifications;
(8) Monitor the scheduling of all construction activities;
(9) Generate the written status report required by Env-Sw 1104.07 at the end of each 2 week period; and
(10) Assure compliance with a quality assurance/quality control plan pursuant to Env-Sw 805.16 if applicable;
(c) If the project engineer is not present at the site when all construction activities at a facility are performed, the permittee shall assure that a qualified resident engineer is present to monitor all construction activities;
(d) The resident engineer required by (c) above shall:
(1) Be a qualified professional engineer; or
(2) Work under the supervision of a qualified professional engineer; and
(3) Be experienced in and knowledgeable about the work he/she shall be overseeing; and
(4) Report directly to the project engineer; and
(e) The requirements of (a) through (d) above shall not apply if:
(1) The permittee has demonstrated in the permit application, or the application for a type II permit modification for construction plan approval, that the nature and scope of the proposed construction activity(s) shall not require professional engineering oversight to assure protection of the environment, public health and safety and to meet other requirements of law; and
(2) The exclusion is approved as a condition of the permit or permit modification.

N.H. Admin. Code § Env-Sw 1104.06

#6619-B, eff 10-29-97; (See Revision Note at chapter heading for Env-Sw 1100) ss by #8459, eff 10-28-05 (formerly Env-Wm 2804.06 )

Amended byVolume XXXIV Number 24, Filed June 12, 2014, Proposed by #10598, Effective 7/1/2014, Expires7/1/2024.