Current through Register No. 45, November 7, 2024
Section Env-Sw 1104.04 - General Construction Requirements(a) Except for the field changes allowed by Env-Sw 1104.05, a facility shall be constructed in strict accordance with the approved plans and specifications.(b) Construction of a facility shall occur in accordance with standard engineering and construction practices.(c) The permittee shall implement quality assurance controls during construction.(d) Construction of a facility shall not take place during climatic conditions having the potential to adversely affect: (1) The quality of the work being performed; or(2) The performance of the facility or any component thereof when operated and closed.(e) The permittee shall assure that construction practices shall comply with all applicable labor safety standards including but not limited to the following: (1) Regulations administered by the Occupational Safety and Health Administration (OSHA); and(2) Statutes and rules implemented by the New Hampshire department of labor.(f) Construction involving the removal or relocation of waste shall occur in accordance with a site safety and contingency work plan as follows: (1) The plan shall satisfy all applicable federal, state and local requirements for protection of human health and the environment; and(2) Except as provided by (3) below, the plan shall be submitted for informational purposes in accordance with Env-Sw 1104.01 including a signed statement by a qualified professional attesting to the adequacy of the plan; and(3) Submittal of the site safety and contingency work plan shall not be required for incidental waste removal such as occurs during gas vent installation.(g) Prior to causing any part of any waste containment, conveyance, processing or treatment system at a facility to become inaccessible for inspection and repair, the system shall be inspected and tested to assure that it meets all applicable standards and specifications.(h) Following completion of inspection and testing pursuant to (g) above, a written inspection report shall be prepared, including: (1) The method of inspection(s);(2) The applicable test protocol and standards; and(3) For a facility which is subject to Env-Sw 1104.06, the professional stamp and signature of the project engineer to certify that, based upon inspection and testing conducted pursuant to the approved design plans and specifications and all additional information known to the project engineer, the applicable facility system has been constructed in accordance with the approved plans and specifications.N.H. Admin. Code § Env-Sw 1104.04
#6619-B, eff 10-29-97; (See Revision Note at chapter heading for Env-Sw 1100) ss by #8459, eff 10-28-05 (formerly Env-Wm 2804.04 )
Amended byVolume XXXIV Number 24, Filed June 12, 2014, Proposed by #10598, Effective 7/1/2014, Expires7/1/2024.