Current through Register No. 50, December 12, 2024
Section Env-Or 307.06 - Approval to Operate Required(a) The owner shall notify the department to arrange for an inspection prior to introducing oil into a newly constructed AST system and prior to backfilling an underground piping system.(b) The department shall grant approval to operate the new AST system only if the department: (1) Determines that the newly-constructed AST system or piping system has been installed in accordance with the approved plans and the terms and conditions of the approval issued pursuant to Env-Or 307.05; and(2) Receives the report from the certified installation supervisor as required by Env-Or 307.09.N.H. Admin. Code § Env-Or 307.06
(See Revision Note at chapter heading for Env-Or 300) #10487, eff 2-7-14