N.H. Admin. Code § Env-Or 306.02

Current through Register No. 50, December 12, 2024
Section Env-Or 306.02 - Spill Prevention Control and Countermeasure Plan
(a) Subject to (f), below, the owner of an AST facility that is subject to this chapter shall prepare and implement a Spill Prevention, Control, and Countermeasure (SPCC) Plan to establish release prevention measures and effective response procedures for releases from the AST system(s) at the facility.
(b) The SPCC Plan shall be:
(1) Prepared as described in 40 CFR Part 112 "Oil Pollution Prevention"; and
(2) Certified by a professional engineer authorized under RSA 310-A to work in New Hampshire (PE), except as provided in (d), below.
(c) The owner shall submit a copy of the signed and PE-stamped certification page of the SPCC Plan to the department within 60 days of implementation of any new or revised SPCC Plan.
(d) In accordance with RSA 146-A:11-c, I-a, the owner of a qualified facility may prepare and implement an SPCC Plan for the facility that is not prepared or approved, or certified, by a professional engineer.
(e) The owner of a qualified facility shall submit a copy of the signed self-certification page of the SPCC Plan to the department within 60 days of implementation of any new or revised SPCC Plan.
(f) An SPCC Plan shall not be required for an AST facility having a combined oil storage capacity of 1,320 gallons or less if all of the following criteria are met:
(1) The facility meets all applicable equipment standards specified in Env-Or 305;
(2) The facility is in compliance with Env-Wq 401.04 relative to storage of regulated substances; and
(3) The facility is not used for fueling water craft.

N.H. Admin. Code § Env-Or 306.02

(See Revision Note at chapter heading for Env-Or 300) #10487, eff 2-7-14