N.H. Code Admin. R. Env-Hw 202.03

Current through Register No. 25, June 20, 2024
Section Env-Hw 202.03 - Timing of Request; Review Process
(a) A request for waiver from the siting requirements of Env-Hw 304.09 shall be made at the time of application submittal under Env-Hw 304.14. The department shall address the applicant's waiver request within the site evaluation required by Env-Hw 304.14(b), which is subject to public review under Env-Hw 304.21.
(b) Other requests for waivers that relate to a permit application shall be submitted to the department with the application or as soon thereafter as the need is identified. The department shall consider the request as part of the application.
(c) Any request that is not covered by (a) or (b), above, shall be submitted to the department as soon as the need for the waiver is known.
(d) Upon receipt of a request for a waiver, the department shall review the submitted information. If the request does not contain all information required by Env-Hw 202.02, the department shall notify the applicant of what information is needed to complete the request.
(e) If a complete request does not provide sufficient information to allow the department to independently conclude that the criteria in Env-Hw 202.04 will be met, the department shall so inform the person who filed the waiver request and offer the person an opportunity to supply additional information. If the person does not supply additional information that is sufficient to allow the department to conclude the applicable criteria are met, the department shall deny the waiver request.

N.H. Code Admin. R. Env-Hw 202.03

(See Revision Note at chapter heading for Env-Hw 200) #9361-A, eff 1-28-09

Amended by Volume XXXVII Number 32, Filed August 10, 2017, Proposed by #12344-A, Effective 8/14/2017.