N.H. Code Admin. R. Env-Dw 723.04

Current through Register No. 25, June 20, 2024
Section Env-Dw 723.04 - Prerequisites to Implementing Approved Non-Central Treatment
(a) Prior to installing any POE or POU treatment devices, the system owner shall:
(1) Develop and obtain approval for a monitoring plan as specified in (b) and (c), below; and
(2) Submit a design layout for the POE or POU treatment devices as specified in (d), below.
(b) The system owner shall develop the monitoring plan required by (a)(1), in consultation with the department, to:
(1) Be consistent with Env-Dw 707 through Env-Dw 713; and
(2) Include provisions for physical measurements, observations such as total flow treated, the mechanical condition of the treatment equipment, the microbiological purity of the water, and scheduled maintenance.
(c) The department shall approve the monitoring plan developed pursuant to (b), above, if the plan is adequate to ensure that the non-central treatment devices will provide health protection equivalent to central water treatment.
(d) The design layout required by (a)(2), above, shall:
(1) Ensure that all consumers will be equally protected;
(2) Provide a POE or POU treatment device for each building connected to the system; and
(3) Include certification from the manufacturer that the POE or POU treatment devices meet the applicable American National Standards Institute (ANSI) even when considering the tendency for an increase in heterotrophic bacteria concentrations in water treated with activated carbon.

N.H. Code Admin. R. Env-Dw 723.04

Adopted byVolume XXXIV Number 24, Filed June 12, 2014, Proposed by #10618, Effective 6/1/2014, Expires6/1/2024.