N.H. Code Admin. R. Env-Dw 1108.14

Current through Register No. 25, June 20, 2024
Section Env-Dw 1108.14 - Final Inspection and Audit
(a) Upon completion of any project for which financial assistance from the DWSRF has been provided, the applicant shall furnish to the department written notification of completion.
(b) Upon receipt of such notification, or upon project completion should notification not be furnished as required, and prior to the department approving the final loan disbursement, the department shall conduct:
(1) A final on-site inspection of the project with the recipient or the recipient's designee; and
(2) An audit of any and all financial assistance funds furnished to the recipient.

N.H. Code Admin. R. Env-Dw 1108.14

Derived From Volume XXXV Number 06, Filed February 12, 2015 , Proposed by #10772, Effective 1/24/2015, Expires1/24/2025.