Section Env-Dw 1108.12 - Approval of Project Modifications
(a) Subject to (b) and (c), below, the department shall approve a request submitted pursuant to Env-Dw 1108.11 if:
(1) The scope of the project as modified is consistent with the original intent of the financial assistance;
(2) The project as modified will bring the water system into compliance with the Act, RSA 485, and applicable rules in subtitle Env-Dw; and
(3) If additional DWSRF funds are requested, the increased cost is approvable under the criteria established in Env-Dw 1108.05(e).
(b) The department shall review the request and notify the recipient and project engineer as soon as practicable considering the scope of the request.
(c) A change of project scope, such as the addition of new construction items, shall not be eligible for additional funding after loan closing unless one of the following conditions are met:
(1) The change of scope is necessary due to an oversight, and is needed to provide an operable water system and not to replace faulty construction or equipment already funded; or
(2) The change of scope is necessary due to changes in federal or state requirements.
(d) The amount of funding provided from the DWSRF shall be increased only by a formal amendment in writing with the department, with governor and council approval.