N.H. Code Admin. R. Env-A 2803.02

Current through Register No. 25, June 20, 2024
Section Env-A 2803.02 - Compliance Testing Requirements for Non-Metallic Mineral Processing Plants
(a) The owner or operator of an affected facility shall conduct a successful compliance test on the affected facility or specific affected equipment, as applicable, in accordance with 40 CFR 60.675 within 60 days of achieving the maximum production rate at which the affected facility or affected equipment will be operated or 180 days after startup, whichever is sooner.
(b) In addition to the compliance test required by (a), above, the owner or operator of an affected facility shall conduct a successful compliance test:
(1) Within 60 days after changing the method of dust suppression used at the affected facility;
(2) Within 60 days after achieving the maximum production rate at which the affected equipment will be operated or 180 days after initial startup, whichever is sooner, if the owner or operator replaces a piece of affected equipment; or
(3) If the test is otherwise required by 40 CFR 60 subpart OOO.
(c) The owner or operator of an affected facility shall not be required to conduct a compliance test solely because the location of the affected facility has changed.

N.H. Code Admin. R. Env-A 2803.02

#6428-B, eff 1-18-97 (formerly Env-A 1210); ss by #8218, eff 11-24-04; ss by #9793, eff 10-1-10

Amended by Volume XXXIX Number 02, Filed January 10, 2019, Proposed by #12693, Effective 12/22/2018, Expires 12/22/2028.