N.H. Admin. Code § Bea 302.08

Current through Register No. 50, December 12, 2024
Section Bea 302.08 - Starting and Completion Dates
(a) Start dates shall be specified on the application and shall be contingent upon notification of grant approval as provided in Bea 304.02.
(b) Project shall start within the current fiscal year.
(c) Completion dates shall be specified on the application.
(d) Projects shall be completed 6 months after the fiscal year in which the grant is awarded.
(e) All reimbursements must be submitted to division of travel and tourism development (DTTD) within 90 days after the end of the current Fiscal Year.

N.H. Admin. Code § Bea 302.08

Derived from Volume XLI Number 41, Filed October 14, 2021, Proposed by #13270, Effective 9/30/2021, Expires 9/30/2031.