Current through October 11, 2024
Section 704A.520 - Advance of portion of estimated costs1. Except for an extension made pursuant to paragraph (a) of subsection 2 of NAC 704A.500, the developer shall pay to the telephone company, in cash before construction is begun on the extension of telephone facilities to and within a development, 50 percent of the estimated costs of constructing the extension within the development and within 100 feet of its boundary, minus any amount previously paid pursuant to subsection 3 of NAC 704A.440.2. The estimated costs must include the cost for preparation or the engineering drawings and designs.3. The estimated costs must not include the cost of:(a) Nonrefundable advances;(b) Conduits and their installation; or(c) Cable used to provide telephone service to persons who reside more than 100 feet from the development or the cost of installing that cable.Nev. Admin. Code § 704A.520
Added to NAC by Pub. Service Comm'n, eff. 3-15-84NRS 703.025, 704.260, 704.280, 704A.300