Nev. Admin. Code § 704.5687

Current through November 25, 2024
Section 704.5687 - Amendment to action plan: Action by Commission
1. The Commission will:
(a) Issue an order approving the amendment to the action plan as filed;
(b) Issue an order modifying the amendment to the action plan; or
(c) Specify those parts of the amendment that the Commission considers inadequate.
2. An amendment to the action plan shall be deemed to be approved by the Commission only as to that portion of the amendment to the plan accepted as filed or modified with the consent of the utility pursuant to subsection 5 of NRS 704.661, as amended by section 2 of Senate Bill No. 87, chapter 230, Statutes of Nevada 2015, at page 1094.
3. If the Commission approves the amendment, the Commission will include in the approval of the amendment its determination that the amendment is prudent. The Commission will make a determination that the amendment is prudent if:
(a) The amendment maximizes the utility's water supply and wastewater treatment capacities for the benefit of the utility's customers; and
(b) The utility demonstrates that the amendment balances the objectives of minimizing cost, mitigating risk and maximizing the reliability of water supply and wastewater treatment for the term of the action plan.
4. If the Commission subsequently determines that any information relied upon when issuing its order approving or modifying the amendment was based upon information that was known or should have been known by the utility to be false when the information was presented, the Commission may revoke, rescind or otherwise modify its approval of the amendment.

Nev. Admin. Code § 704.5687

Added to NAC by Pub. Utilities Comm'n by R043-08, eff. 9-18-2008; A by R110-15, eff. 6/28/2016

NRS 703.025, 704.210 and 704.661, as amended by section 2 of Senate Bill No. 87, chapter 230, Statutes of Nevada 2015, at page 1094.