Section 704.9508 - Update of energy supply plan: Action by Commission1. The Commission will conduct a hearing within 60 days after a utility files an update of its energy supply plan pursuant to NAC 704.9506 and issue an order within 120 days after the filing of that update by the utility pursuant to NAC 704.9506.2. The Commission will conduct its evaluation of the update of the energy supply plan in accordance with NAC 704.9494.Nev. Admin. Code § 704.9508
Added to NAC by Pub. Utilities Comm'n by R004-04, eff. 5-25-2004NRS 703.025, 704.210, 704.741