All costs of a replacement project proposed in an advance application submitted to the Commission must be accounted for in the books and records of a gas utility separately from amounts attributable to any other activity. Each regulatory asset account must be maintained in a manner that will allow costs to be readily identified.
Nev. Admin. Code § 704.7979
NRS 703.025, 704.185, 704.210