Current through November 8, 2024
Section 703.185 - Specific requirements for electric companiesIn the case of an electric company, in addition to all other applicable requirements of NAC 703.175, an application must include:
1. Load and resource data setting forth recorded and estimated loads (energy and demands), available capacity and margins for 2 years of actual and 3 years of estimated, on the basis of an average year.2. The effective operating capacity of generating plants which have been rated and planned additions for the next 3 years.3. The estimated capital and operating costs of any proposed generating plant.4. The estimated number of customers to be served and their requirements for the first 5 years of operation.Nev. Admin. Code § 703.185
Pub. Service Comm'n, Gen. Order 3 part § 19.020, eff. 1-1-79