Section 625.490 - Notification of failure to complete required number of professional development hours

If the Board accepts less than 30 professional development hours for which a licensee submits proof of completion pursuant to NAC 625.430, the Board will notify the licensee not later than 60 days after the date on which the application for renewal was submitted that:

1. The licensee must successfully complete the number of professional development hours which are deficient within 6 months after the date on which the application was submitted; and
2. The licensee's failure to complete those professional development hours will result in the licensee being placed on inactive status.