Nev. Admin. Code § 624.015

Current through October 11, 2024
Section 624.015 - Exemption for owner-builder: Procedure
1. To apply for an owner-builder exemption from the provisions of chapter 624 of NRS pursuant to subsection 4 of NRS 624.031, an owner of property must submit an Owner-Builder Disclosure Statement to:
(a) The Board; and
(b) The local building official responsible for issuing the permit for the work that will be the subject of the exemption.
2. If the Owner-Builder Disclosure Statement submitted pursuant to subsection 1 is completed fully and accurately, and signed by the applicant under penalty of perjury, the Board will approve the owner-builder exemption.
3. Unless the Board notifies the applicant within 10 days after he or she submits the Owner-Builder Disclosure Statement to the Board that the owner-builder exemption is denied, the owner-builder exemption shall be deemed to have been approved by the Board.
4. If the Board denies an application for an owner-builder exemption, the Board will, within 10 days after the applicant submits the Owner-Builder Disclosure Statement to the Board:
(a) Notify the applicant that the owner-builder exemption is denied; and
(b) Set forth the reasons for the denial.
5. If the applicant is notified pursuant to subsection 4 that the owner-builder exemption is denied, the applicant may submit supplemental materials to the Board regarding the application for an owner-builder exemption.
6. If it appears to the satisfaction of the Board that the materials submitted pursuant to subsection 5 satisfy the reasons for the denial of the owner-builder exemption, the Board may approve the owner-builder exemption.
7. As used in this section, "Owner-Builder Disclosure Statement" means the form adopted by the Board pursuant to NAC 624.017.

Nev. Admin. Code § 624.015

Added to NAC by Contractors' Bd. by R047-03, eff. 12-4-2003

NRS 624.031, 624.100