Within 30 days after the completion of the construction of a geothermal well listed in this section and the removal of the drill rig from the location of the well, the person who holds a permit to drill or operate an individual geothermal well or a permit to drill or operate geothermal wells in a project area shall pay to the Division a fee based on the depth of the well according to the following schedule:
INDUSTRIAL WELLS | 300 to 1,000 Feet Deep | 1,001 to 5,000 Feet Deep | Over 5,000 Feet Deep |
Production Well | $1,000 | $2,000 | $2,500 |
Injection Well | 1,000 | 2,000 | 2,500 |
Observation Well | 300 | 500 | 2,500 |
COMMERCIAL WELL | 200 | 200 | 200 |
Nev. Admin. Code § 534A.216