Nev. Admin. Code § 519A.175

Current through August 29, 2024
Section 519A.175 - Time for final denial or issuance of final permit; effective date of permit; notice of denial
1. The Division shall issue a final permit to the applicant or a final decision to deny a permit within 15 days after:
(a) If a public hearing is required, the close of the period for submitting comments and information prescribed in NAC 519A.185 to 519A.210, inclusive; or
(b) If a public hearing is not required and the application is complete, the receipt of an application for a permit and the required fees.
2. A permit issued by the Division becomes effective upon the receipt by the Division of the surety required by NAC 519A.350.
3. If the application for a permit is denied, the Division must notify the applicant of:
(a) The reasons for denial; and
(b) The time within which an appeal must be brought and procedures for appealing the decision pursuant to NAC 519A.415.

Nev. Admin. Code § 519A.175

Added to NAC by Environmental Comm'n, eff. 9-19-90

NRS 519A.160