Current through November 8, 2024
Section 519A.125 - Permits for exploration projects: Application1. The operator of an exploration project shall apply to the Division for a permit.2. The application must include: (a) The applicant's name, address and telephone number;(b) If the applicant is a corporation or other business entity which is required to have a registered agent, the name, address and telephone number of its registered agent and its principal officers or partners;(c) A complete plan for reclamation;(d) The estimate of the cost of executing the plan for reclamation required by NAC 519A.360;(e) A statement that the applicant agrees to assume responsibility for the reclamation of any surface area affected by his or her exploration project;(f) A map which depicts the area to be covered by the surety;(g) For the purpose of calculating the amount of the surety, the average number of drill holes to be left open at any one time during the life of the project; and(h) An affidavit that meets the requirements set forth in section 3 of this regulation.3. The application must be accompanied by the fee charged by the Division for an application for the issuance of a permit required by NAC 519A.225.Nev. Admin. Code § 519A.125
Added to NAC by Environmental Comm'n, eff. 9-19-90; A 9-5-91; A by R085-21A, eff. 4/1/2022NRS 519A.160, 519A.190, as amended by section 1 of Assembly Bill No. 148, chapter 385, Statutes of Nevada 2021, at page 2339