Current through December 31, 2024
Section 512.577 - Requirements for reinstallation1. If a boiler or pressure vessel is removed from its original site and reinstalled at the same location or reinstalled at a new location without a change of ownership before reinstallation, the contractor must submit to the Administrator a notice of installation before installing the boiler or pressure vessel. The fittings and appurtenances must comply with the requirements for the installation of a new boiler or pressure vessel.2. If a standard boiler or pressure vessel is to be moved to another state for temporary use or repair, the owner or user must notify the Administrator in writing before reinstalling the boiler or pressure vessel within this State.3. As used in this section, "standard boiler or pressure vessel" has the meaning ascribed to it in NAC 455C.102.Nev. Admin. Code § 512.577
Added to NAC by Div. of Industrial Relations by R141-98, eff. 1-28-2000; A by R026-23A, eff. 9/16/2024