Section 477.840 - Certification of proper installation; metal placard required
1. Following the installation of a fire standpipe system, the licensee shall submit a letter to the authority having jurisdiction certifying that the system has been installed in accordance with the plans approved by the authority having jurisdiction and all applicable state and local codes.
2. Within 30 days after completing the installation or remodeling of a fire standpipe system, the licensee shall attach a metal placard which must:
(a) Identify all requirements for the hydraulic design.
(b) The number, size and location of system outlets and the calculated discharge of the highest outlet.

Nev. Admin. Code § 477.840

Added to NAC by St. Fire Marshal, eff. 3-9-89; A by R062-04, 9-3-2004